Modifying a Schedule
FlexNet Manager Suite ()
Changing a schedule affects all activities (or connections) attached to the schedule.
-
To modify a schedule:
-
Run the inventory beacon interface (for example, in the Windows Start menu, search for FlexNet Beacon, right-click it, and select Run as administrator).
Tip: Remember that you must run the inventory beacon software with administrator privileges.
-
From the Data collection group in the navigation bar, choose Schedules.
-
In the list of available schedules, click a row to select the schedule you want to change, and then click Edit....
The Edit Schedule dialog appears.
-
Modify the schedule settings as required, and click OK to update the schedule in the listing on the Scheduling tab.
-
Remember to click Save to record your changed list of schedules.
Parent topic:Scheduling Tab